Legal routes for conflict resolution

1. Introduction
IT disputes do not always unfold predictably. Discussions about scope, quality and costs frequently arise during an IT project. Supplier and customer are generally aware of this, but find it difficult to make these issues negotiable.
Careful negotiations and accurate agreements can ensure that the customer’s assignment becomes clearer and parties expectations are more aligned during an IT project. In practice, there is still much to be gained here.
Once the contractual phase is over and the IT project is being implemented, the law provides tools to minimize risks early on. This goes beyond sending a formal notice of default once all hope of a successful outcome has been dashed.
Inspired by our legal roadmap (see above), in this blog we discuss some legal tools that parties can use to make earlier adjustments to an IT project in danger of stalling.
2. “Pay attention!”
Many IT implementation projects qualify as a contract of assignment. This obligates the IT supplier to exercise the care of a good contractor in his work.
Part of this duty of care is that an IT supplier must keep its customer informed of its work (duty of information). The IT supplier must also warn its customer of risks involved in the project (duty to warn).
In case law on failed IT disputes, customers regularly successfully invoke this duty of care on the part of the IT supplier. For example, an IT supplier breached its duty of care because the agreed upon IT package (an “all in package”) that would be delivered did not include security. The IT supplier should have warned that security was lacking. By not doing so, the customer could expect, based on the duty of care, that security was present in the total package to be delivered.
IT suppliers should also also warn customers if the customer’s IT infrastructure is of insufficient quality for the task to be performed. Especially if an IT supplier profiles itself as an expert in a particular industry, this creates an expectation among customers that the software to be delivered is tailored to the industry. It is up to the IT supplier to manage these expectations. We recommend that IT suppliers inform their customers about the risks in advance, but also warn about newly emerging risks in the interim.
3.”Listen up!”
The customer – when it concerns a contract of assignment- has a right of instruction. The IT supplier will have to follow responsible instructions from the customer, for example if the customer asks the IT supplier to first focus all energy on solving a specific problem such as resolving issues with operational software and only then proceed with new implementation work.
There is, of course, a limit to this right of instruction. If the IT supplier cannot agree with the customer’s instructions, then the IT supplier can (and perhaps should?) ignore them. If the customer does not accept this, the IT supplier can terminate the agreement with the customer (see point 6). This may be the case, for example, if the customer refuses to purchase any form of security.
4.”Do something yourself!”
Many IT suppliers have experience with customers who do not cooperate adequately or with fickle decision-making by a customer that impedes the progress of an IT project. It is not easy to hold a customer accountable for this.
A balanced IT agreement is characterized by obligations for both the IT supplier and the IT customer. This can relate to practical matters such as the timely delivery of information as well as more formal aspects such as the adequate performance of an acceptance test.
Ofcourse both parties can reciprocally claim fulfillment of their respective obligations. Thus, an IT supplier can also claim fulfillment of required cooperation. However, the condition is that the obligation is due and that the other party cannot successfully invoke a right of suspension.
A customer who sued an IT supplier because the IT supplier would not honor the agreement was confronted with the IT supplier’s defense that the customer’s IT environment did not meet the requirements that the parties had previously agreed upon. The court agreed and the IT supplier’s liability was reduced.
A customer who under the agreement was responsible for testing the new software, but had not done so adequately, could not hold the IT supplier accountable at a later date that the software was defective.
5.”I’m not doing anything more for now!”
Suspension is usually not an issue in IT conflicts until the dissatisfied customer decides to stop paying. By then, the expected budget has often been greatly exceeded and the relationship severely disrupted.
Not only the customer but also the IT supplier can invoke the right of suspension. Using the right of suspension does require due diligence, especially if the customer’s primary business processes depend on the IT supplier’s services.
An IT supplier need not wait to suspend until the customer stops paying (to legitimize the cessation of work). (Partial) suspension can also be a useful tool if the project is not going well because the customer does not cooperate (in a timely manner).
6.”I quit!”
Sometimes courts rule that the IT supplier should have decided to (temporarily) stop the IT project because of unreasonable demands and expectations of the customer. Indeed, an IT supplier is entitled to terminate the agreement if the IT supplier demands fulfillment of unreasonable instructions.
Although this is formulated in the law as a right to refuse, case law shows that an IT supplier may even be obliged to refuse (further) cooperation if an IT project gives cause to do so based on its own professional responsibility (duty of care). For example if a customer refuses to realize any form of security of the IT systems. Also when it is clear to the IT supplier that a project is not going to benefit the customer, the IT supplier should, under circumstances, push for termination.
7.”We’ll figure it out together.”
Mediation is an alternative form of dispute resolution that is ideally suited to restarting a conflict that is derailing.
Unlike in the court system, in mediation all interests of the parties play a role in the resolution of the conflict, including, for example, commercial interests or the interest in preserving the relationship for the future. Parties choose mediation voluntarily and strict confidentiality applies so that parties can reach a solution in confidentiality. Mediation can often achieve a solution much faster than legal proceedings. We therefore often recommend that clients try at least one mediation session.
With some regularity, an IT agreement includes a mediation clause. A mediation clause does however not by definition preclude going to court.
8. Completion
The legal toolbox contains many more tools to adjust an IT project than just sending a notice of default after the customer has (finally) decided to suspend its payment obligation. Some examples have been mentioned above.
In practice, however, it is important to keep the legal agreements connected during the course of the IT project, that is, even while the parties are executing the agreement. In other words, the agreement must also be adhered to.
If, in practice, the parties start implementing the IT project very differently, then it becomes more difficult to demand compliance with that agreement at a later stage. Although the agreement can be filed in the drawer, it must be dusted off regularly!